I created a separate sub-task workflow that only includes 4 status values. There are two that show as green values to indicate final status ("Cancelled" and "Done - Complete"). However, now when I try to close the sprint, I get a message that the following issues have sub-tasks that are not closed. When I go to the issues in question and review the sub-tasks, they all appear to be in the Done - Complete status.
Is there some other way I need to identify the sub-task Done - Complete status = closed?
What gives? I cannot seem to identify what needs to be done to close the sub-tasks?
Dose these 4 subtasks contain both “Done - Complete” and "Cancelled" statuses?
You can try to check the column management in the board configuration. Both of these final states match the Done column?
Thanks @Ollie Guan. The column was already setup as such. After trying again the following day, it allowed me to close the sprint. I did republish the workflow, but I can't see how that would have fixed the problem. Either way, it works now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you!! After studying all day, I didn't think it was so easy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This answer solved my issue also. How simple can it be! Thank you!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.