We are looking to produce Velocity chart report.
It looks as if xxxx Sprint 1 and xxxx Sprint 2 did not have the 'Story Point' values input before closing the sprint. They have entered their values now. Is there anyway to update the chart to include the 'Story Point' values in the chart (both committed and completed).
Thanks!
There's no way to do that.
The problem here is that you didn't have a velocity in those closed sprints because you didn't estimate and start the sprint with any knowledge of what you had committed to. The charts are actually accurate already, you can't change the history.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.