Velocity calculation over last X sprints in GreenHopper

Dirk_Maucher
Contributor
March 19, 2012

I was not able to find a possibility in GreenHopper to show me the calculated velocity over the last X sprints.

Currently we do this manually: we add together the story points of the last 3 sprints and divide the result through 3 (sprints).

Is this also possible with GreenHopper? If not would it be possible to add this as a feature in the upcomming versions?

1 answer

1 vote
boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 21, 2012

This can be done using the Agile gadget which has a velocity tab, you will have to select each sprint from the dropdown in turn.

Alternatively if you have it setup so you have a "Feature backlog" as the parent of all issues then when looking at the statistics burn down chart for story points you will see an option under daily called children which opens up a histogram of your velocity burndown sprint by sprint.

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, aafp, jira migration, marketing collaboration, end siloed work, streamline workflows, kerrie gottschalk, jira cloud admins, unified marketing, process visibility, team efficiency, cross-team collaboration

How Kerrie Gottschalk unified AAFP’s marketing team with Jira

At the American Academy of Family Physicians, siloed marketing teams faced delays and duplicate work. Kerrie Gottschalk shook things up by moving the department to Jira, streamlining processes, boosting visibility, and sparking stronger collaboration.

Read the story
AUG Leaders

Atlassian Community Events