Hi all,
When creating my Jira backlog I have created interdependencies within it for example x task releases x. However, I am struggling to see this visual representation with my BigPicture boards I have created. Is there a way that I can view this rather than duplicating the effort and drawing the lines via BigPicture?
Thank you.
Hi, @Alasdair McKie !
If I correctly understand your problem - you should configure link type in BigPicture settings.
Docs about this - Global configuration - Link configuration.
Exactly as @Alexander Bondarev has mentioned, you should map Soft Links to the link type you used. Please see my image as a reference.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
at top bar in dependencies menu, just set Display to Expanded. and then you can see dependency lines visually
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are welcome @Alasdair McKie
In case of other questions connected with BigPicture, just tag me in your thread!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!
Register today
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.