Where a free text searcher field takes the information from?

natalia_sandakova June 15, 2023

Howdy)

We came across a case where our custom field either stopped working or is working incorrectly.

We have an automation rule that evrey Monday creates and sends an email with following content:

email.png

"Countdown" and  "Планова дата виконання" (equivalent of  "Due date") are custom fields.

As they told me "Countdown" should have count how many days we have left till the Due date, the number should automaticcally change everyday (I have no idea what it should do when the Due date has passed, show "0" maybe, IDK). Here is the details of the "Countdown" field (there is no description):

countdown.png   

As I understand his field doesn't count anything, it reads the text from some source and shows it. I need to find where it takes the nubmer of remaining days from.

I understand that you don't see the whole system, but maybe you can suggest what mechanism in Jira can count the days from current day till "Due date" (or other relevant field).

Thank you and have a good one)

2 answers

1 accepted

0 votes
Answer accepted
natalia_sandakova August 1, 2023

I found out that we had a rule that makes a meaning for that field)

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 15, 2023

HI Natalia,

Maybe create a custom field of Number type. Then create a scheduled automation rule that calculates the difference between now() and you custom due date field and store it in terms of days in the number field. Then you can use that field in your notification. 

Suggest an answer