Why the option of burndown chart not showing up in project?

Kartik Gupta March 11, 2019

On a particular Jira Project, I don't see the Burndown chart under the 'Report' navigation whereas I see that chart in all of my other projects. 

Do I turn something on to show this report for a specific project?

1 answer

1 accepted

0 votes
Answer accepted
Taranjeet Singh
Community Champion
March 11, 2019

@Kartik Gupta The project in question may not be a Scrum Project. The "Burndown Chart" is only available for Scrum Projects/Boards. Please see this: https://confluence.atlassian.com/jirasoftwareserver0713/burndown-chart-965542661.html

Kartik Gupta March 11, 2019

Is there an easy way to find the type of project that is? I'm assuming somewhere in the Project Settings this information is available.

Suggest an answer

Log in or Sign up to answer
TAGS
Atlassian, Team '25 Europe, Atlassian conference, AI-powered teamwork, Atlassian events, keynote speakers, Barcelona tech conference, Atlassian Williams Racing, Carlos Sainz, Jenson Button, Mike Cannon-Brookes, Anu Bharadwaj, Atlassian Rovo

Atlassian Williams Racing is coming to Team '25 Europe 🏎️

Discover the teamwork and precision behind success on and off the track. See how this high-performing team makes the impossible possible. Be one of the first 100 customers to register for a chance to win 2 tickets to an Atlassian Williams 2026 race.

Register now
AUG Leaders

Atlassian Community Events