does the project key change when you bulk move issues from one project to another?

Ben Rejab Rim
Contributor
August 15, 2024

Hi folks,

Does the project key changes to the source project if you bulk move issues from one project to another?

thanks a lot ^^

Rim

1 answer

1 accepted

1 vote
Answer accepted
Dexter de Vera
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 15, 2024

Hi @Ben Rejab Rim ,

Yes, all issue moved to another issue will update the issue key base on project key of the destination project. But the old issue key of the issues still can be search via filters.

Hope it helps,

Thank you.

Ben Rejab Rim
Contributor
August 15, 2024

okkay thanks,

because I have seen some videos where the filter shows two keys (old and new project) while on the board we can only see one key.

Thanks again Dexter