how to add other field sub-task preview

구본석
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 29, 2024

 

When a sub-task is created in a JIRA issue card, a brief preview of the sub-task is shown.

Currently, the sub-task card shows the number, summary, assignee, and status. How can I make other fields visible in this preview as well?

 

2 answers

1 accepted

2 votes
Answer accepted
Trudy Claspill
Community Champion
July 29, 2024

Hello @구본석 

Welcome to the Atlassian community.

If you are referring to the list of subtasks that appears in the details view of the parent issue, then it is not possible to customize that at this time. There is an open change request for that to which you can add your vote:

https://jira.atlassian.com/browse/JRACLOUD-70206

1 vote
Avery
Contributor
July 29, 2024

To make sub-task previews different in JIRA, you need to change card layout settings on board. First, go to your board and find the three dots (or maybe it looks like a gear) at top right corner. Click there and choose "Board settings." From that place, choose "Card layout." Additional fields can be added to the sub-task preview by picking the fields you wish from the dropdown menu. Save your changes, and the sub-task cards now show extra fields you chose.