Hi,
We are using Jira server.
Teams are working SCRUM.
We use Jira Plans (formally portfolio) to manage the progress - such as PI progress that includes all Epics per PI.
we would like to manage additional things and need a solution for those two items:
1. Option to set the epic summary on the epic progress bar.
Today, you alwas neeed to scroll to the left side in order to see the issue name / summary.
2. option to manage milestones in Jira plans. My current solution is using a new issuetype and assign same start / end date, so it will appear as milestone without a duration.
Any other better solutions?
Thanks,
Yaron
For #1, there is no way out of the box to accomplish that. If you are open to using a 3rd party plugin, something like BigGantt can do both things you are looking for.
For #2, we also have decided to use a custom issue type for Milestones and this has worked fine for our needs.
Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.
Register nowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.