Idris Gagan February 16, 2015

I moved all the issues from Project A to Project B. All of the standard issues moved fine but the sub tasks did not move. Now I have issues in Project B and their sub tasks in project B. How do I make the sub-tasks to move to project A? It is become really difficult to track issues and sub tasks, even though linked, they are in two different projects.

1 answer

0 votes
AgentSmith
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 23, 2015

The bulk move operation can be performed on both standard issues and sub-task issues but you need to move the sub-task to a new issue type based on issue's parent project that it moved too.

More details on that here:
https://confluence.atlassian.com/display/Cloud/Modifying+Multiple+('Bulk')+Issues#ModifyingMultiple('Bulk')Issues-bulkmove

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, loom, AI, meeting recording, community

[NEW] Record your meetings with Loom

Welcome to great meetings, with less work. Automatically record, summarize, and share instant recaps of your meetings with Loom AI.

Learn more
AUG Leaders

Atlassian Community Events