I have Project P1 and Project P2.
I have 2 stories in P1. They are P1S1 and P1S2
And I have 1 story in P2. It is P2S1.
Now, I have created a FixVersion V1.
I want to link P1S1 and P2S1 to V1 because both as to go live together and should have the same fixversion.
Is this possible?
It is possible, but you would need an app to sync versions, since they are project specific. Version Sync is the only one I found on Marketplace that can do that.