Hi,
How are teams and individual capacity planning is done using Structure Gantt ( Agile).
I see we need to create a custom field Team with team name only but it doesn't represents team members to understand what is the capacity of the individuals during the sprint.
Any information would be really helpful.
Thanks,
Vijay
Hello Vijay,
It looks like you've already written to our support and got an answer from my colleague, but I'd like to post his answer here as well, if other community users are interested in this topic.
Currently resource management functionality in Structure.Gantt is limited, so there is no actual connection between different resources (there is no resource groups and various availability schedules are not connected between structures as well). We are working on improving resource management, but there is still a lot of things to be done in that direction
You can learn more about Resource management in Structure.Gantt in our documentation: https://wiki.almworks.com/display/gantt/Working+with+Resources
Kind regards,
Daria
[ALM Works]
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.