Checklist Pro question. Block closing of task until checklist is complete

Michael Arndt
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 14, 2019

Is there a way to prevent a task from being closed if there's any unchecked items on a checklist?

2 answers

2 votes
Paweł Albecki
Contributor
August 14, 2019

Hi!

It is possible. This tutorial should help: https://gebsun-support.atlassian.net/wiki/spaces/IC/pages/728039472/Block+workflow+transition+if+checklist+is+not+complete.

You could also give a try to my app Multiple Checklists for Jira. Blocking transitions feature, such as preventing a task from being closed, is described here.

Best,
Paweł

0 votes
Jack Hunter _HeroCoders_
Atlassian Partner
August 14, 2019

Hi @Michael Arndt

As already mentioned the Checklist Pro and Checklist Free allow to block transition if the checklist is not completed. 

The configuration process is described here: https://gebsun-support.atlassian.net/wiki/spaces/IC/pages/728039472/Block+workflow+transition+if+checklist+is+not+complete

Let us know in case of other questions. We are happy to help.

Cheers,
Jack