Is it possible to move a card based on a date set in a custom field?
I have several custom fields created with different dates, and I would like each card to automatically move to another list when its respective date arrives.
I’ve tried a few times to set this up, but I couldn’t get it to work.
Thank you for reaching out to the Trello Community!
You can create a scheduled automation rule that will run each day (can even select specific time) and will look for the custom field value of all the cards of the board to see if the date in the custom field's date matches today's date. It can then move the card to the required list.
Here's an example:
Here's how you can set the above action in the rule:
Hope this helps!
Thanks & regards,
Lipakshi Narang