Hi all!
Recently I faced the problem of finding a way to sum up the original estimate of all issue types of an epic, without the use of an addon. I was going to use only the native automation that Jira provides. At first my manager gave me a hint of this example to follow and I thought that "hey! I could use this to solve my problem in no time!".
How little did I know :D
This example worked perfectly when you had stories and subtasks and you wanted to sum up story point. However my problem was a bit different. I had 4 different issue types (standard tasks) from which I wanted to sum up all original estimates and not story points. Long story short, after trying numerous ways and quite a few community proposed solutions, which in my case they didn't work, I came up with a kinda good workaround.
Below you will find my rule, which after testing it, it works like a charm:
So what the above rule does is that
Below you will find each individual rule component.
"Epic Link" = {{issue.key}}
{
"fields": {
"timetracking": {
"originalEstimate" : "{{lookupIssues.Original Estimate.sum .divide(60)}}",
"remainingEstimate" : "{{lookupIssues.Remaining Estimate.sum .divide(60)}}"
}
}
}
I though to end this discussion by presenting to you the pros and cons of this rule, as well as my justification in creating and following it.
I would very much like to discuss about this solution, and if you have anything better to suggest please do share!
Cheers,
Alex
Alex Koxaras _Relational_
Atlassian Solution Architect
Relational
Athens, Greece
1,366 accepted answers
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
67 comments