Background:
Our QA team needs to know when the parent task is in Demo, which is tricky because part of it might already be in production by the time the last subtask gets to Demo. So I need to be able to update the parent IF
I have the following rule set up in automation:
Action: When value changes for Environment
If: Environment = Demo
For Parent
I think this might work, but I am worried about things where there is only 1 subtask, and if it moves to Production, would it then update the parent to Demo? We have separate automation that updates the parent Environment to Production if all subtasks are in Production, but you can't force order of execution of rules, so I'm worried it'll move Environment back to Demo even though it should be Production.
Thoughts?
Hi @abby.kaske
For your special case of one-and-only-one subtask, you could use the Lookup Issues action to gather up all subtasks/siblings of the trigger issue with JQL, and then check if there is only one with an advanced compare condition...plus any if/else structure you need to support it.
Kind regards,
Bill
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.