×Hi,
A resource has workload plan with 8 hours and he is assigned to a task (no subtasks) that has 20 hours original estimate.
We have indicated 4 hour/day in Time Tracking configuration of Jira and BigPicture calculated end date based on 4 hour/day and distributed effort based Workload Plans of resource. Why? The task should end when all the effort is distributed (Oct 17th) , right?
(screenshoots attached)
Thanks
Sorry, an error in a previous message: "The task should end when all the effort is distributed (Oct 18th) , right?"