Business Timeline to Software Timeline

Anita Pallas December 5, 2023

We have created the events planner which is a business project however the timeline doesn't seem to allow you to dropdown epics to show tasks.

Nor does it let you open the task on the right hand side.

However software projects let you.

Is there a way to do this in the business planners?

1 answer

1 accepted

0 votes
Answer accepted
Linh Pham_Ricksoft_Inc
Community Champion
December 5, 2023

Hi @Anita Pallas and welcome to the Community!

Unfortunately, only the List view supports the hierarchical view of Epic > Story > Sub-task, here's the feature request https://jira.atlassian.com/browse/JWMCLOUD-30 (you can vote on the related sub-task to support hierarchy on timeline https://jira.atlassian.com/browse/JWMCLOUD-111)

Cheers,

Linh

Anita Pallas December 6, 2023

thanks