Can I configure the fields on a subtask to be different than the parent task?

Bobbi Jo Shortt August 31, 2020

I want the fields on certain types of subtasks to require different information than the parent task. Is this possible?

1 answer

1 accepted

0 votes
Answer accepted
John Funk
Community Champion
August 31, 2020

Hi Bobbi Jo,

Yes, you can create a different Field Configuration for each issue type. Then all of the Field Configurations are grouped together in a Field Configuration Scheme and the scheme is attached to the project.

Each Field Configuration can have different required fields. 

Likewise, you can have different screens attache to each Issue Type using the Issue Type Screen Scheme. 