Change of status to Done at parent level when child status changed to Done

sarathgd
Contributor
August 22, 2022

Hi,

I have a structure with different issue types (Feature, Story, task etc.) and programme name as parent. I have start date and end date associated with each status. When the status of all the child's (feature >> Story >> Task etc) moved to 'Done' status, I want my parent status (Programme name ) also need to be changed to 'Done'.

Is there any way I can achieve this by using any formula?

Appreciate any help here.

Thanks,

Sarat Chandra

 

3 answers

1 accepted

1 vote
Answer accepted
Yulia Barbash _ALM Works_
Atlassian Partner
August 24, 2022

Hello Sarat,

Yulia from ALM Works here.

Unfortunately, it is not yet possible on Structure Cloud.

But we have plans to implement the "Status rollup" feature, and if you like I can add you to the notification list when it is available. 

Best regards
Yulia Barbash

sarathgd
Contributor
August 24, 2022

Thanks Yulia for response, 

Yes, please add me to the notification list.

sarathgd
Contributor
September 13, 2022

One more question on this topic, I'm using JIRA Onprim version. 

Is this status rollup in structure feature available in JIRA DC/Onprim versions?

 

Thanks in advance,

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 22, 2022

Hi @sarathgd 

Create an automation rule similar to below. I do it as a scheduled trigger that fires once a day so it doesn't fire on every issue that moves to Done. You could run it more frequently if you want. 

Screenshot.png

sarathgd
Contributor
August 23, 2022

Thanks John for help here. I think the automation you suggested is at Project level.  If I do this automation at project level, I guess this rule will be triggered when ever any change at issue type every time.

But I need this functionality at Structure level, I don't want to disturb anything at project level. Is there any way I can implement this change of status at parent level once the status of child issues moved to 'Done' by using any formula?

 

Thanks for your help in advance.

John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 24, 2022

Sorry, but that structure is a little beyond me.

0 votes
Mohamed Benziane
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 22, 2022

Hi,

You can try to achieve this by using Automation for Jira