Changing estimate times on Kanban from hours to days

Hannah Johnson
Contributor
September 1, 2023

Hello, 

I am looking for some help with changing the estimation times on a JIRA Kanban board from hours to days. For example, every time I put 4 days it automatically changes to 96 hours but my team would prefer to see the days. I have tried putting 4d but again it doesnt work. Does anyone have any suggestions? 

the project is on the company managed software setting

1 answer

1 accepted

1 vote
Answer accepted
Manoj Gangwar
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 1, 2023

Hi @Hannah Johnson ,

Welcome to the Atlassian Community!!

If you have Admin permission then you can go into Settings -> Issues -> Scroll down to Issue features, then time tracking you will be able to configure everything in there from how to view, to working hours per day. 

Hannah Johnson
Contributor
September 1, 2023

Thank you so much!! It took me a while to find the time tracking part but its now fixed! 