We have a small dev team that works on tasks from multiple projects in each sprint - for example, during a sprint they will work on tasks from:
The only way I can do this at the moment is to have ALL of our tasks on one board so that I can put them into the same sprint.
I can't find anything that definitively says this is possible - can anyone help?
We use JIRA Cloud Team Managed Projects.
Hi @therjmb,
You are basically right that you need to have all your tasks in one board if you want to put them in a single sprint. This is simply because a sprint is a feature of a scrum board (company managed) or a specific feature that you can enable in the feature set of a team managed project.
You do not need to put all your tasks in a single project, but in order to work across multiple projects with a single board, you should really use company managed projects. Team managed projects are designed to be used in isolation and are not a good fit for your use case.
For more information on setting up a board across multiple company-managed projects, see the following support articles:
Hope this helps!