I have an automation that creates two tasks every time a story is created. I need those two tasks to have the Due date assigned automatically from the trigger issue (story) Due date.
Can someone answer this challenge?
Have you tried to set the Due Date field using the option Copy from Trigger Issue when you create them? You can find that under the ... options to the right of the field:
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Show up and give back by attending an Atlassian Community Event: we’ll donate $10 for every event attendee in March!
Join an Atlassian Community Event!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.