Estimated time in next generation projects

Maribel Pinillos December 9, 2020

Hello,

Does anyone knows how can I add ESTIMATED TIME in an issue on NEXT GENERATION PROJECTS?

Thanks,

Maribel

1 answer

0 votes
Stuart Capel - London
Community Champion
December 15, 2020

Hi Maribel,

 

You'll need to be able to add fields to achieve this. If you go to 'actions' > configure

Capture.JPG From here you can add fields - if you drag 'Time tracking' into the context fields, you'll get a field where you can add remaining and completed time.

Capture.JPG To add your estimate just enter the 'time remaining'

Capture.JPG

 

Let me know how you get on and if you need any further assistance :)

Maribel Pinillos December 16, 2020

Thank you!

Like Stuart Capel - London likes this