How can we see sub-tasks on the kanban board along with respective story?

1 answer

1 accepted

2 votes
Answer accepted
Walter Buggenhout
Community Champion
July 24, 2022

Hi @Sandeep Agrawal and welcome to the Community!

If you are using a team managed project, select the option group by subtask near the top right of your board:

Screenshot 2022-07-24 at 21.35.25.png

In a company managed project, you can set up swimlanes by stories via board settings > swimlanes:

Screenshot 2022-07-24 at 21.37.46.png

Hope this helps!