Dear Community,
I have created a new team in my roadmap under the "Team" tab and given it a weekly working time.
My goal is to assign stories to this team. However, I have only found out how to assign stories to individual team members.
What is the purpose of a created team if this is not possible?
I would be very pleased to receive an answer!
Hi @Ricardo Schmadalla !
You can't assign a whole issue to a team. Assignee can only be one user. In order to assign a team, you need to either
However in comments you can mention a whole team by selecting the "@" and then the team name.
Alex
Hello Alex, thank you very much for your answer.
That's a pity that it doesn't work.
I thought it was possible to distribute the weekly working time of a team among the different tasks.
Why is there the function of weekly capacity if you can't use it further?
Basically, I want to derive my resource needs from the roadmap. Do you see any other way to do this?
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you have the Premium plan of Jira you will be able to use this feature as stated here:
https://confluence.atlassian.com/advancedroadmapscloud/teams-998650939.html
But since you are running on a standard plan, this is not possible out of the box.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.