Hello everybody,
we have milestones that are cross-project. Can you assign a milestone to multiple projects?
Thank you in advance
Trust you are well.
For most cross-project things you need an App. Advanced Roadmap might be an option to track cross project milestones as cross project releases.
If you decide to check out the Apps I would suggest to look at Release Management for Jira. Here you can add cross project releases with custom workflows and define intermediate release milestones.
Many thanks & Kind regards,
Yuri.
Short answer is unfortunately, no. Versions are project-level configuration, not global within Jira.
Advanced Roadmaps is probably going to be the best tool out there for you, for configuring cross-project releases. Doc for ref: https://support.atlassian.com/jira-software-cloud/docs/create-a-cross-project-release-in-advanced-roadmaps/
Hope that provides a bit of insight - Steve.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.