Just a heads up: On March 24, 2025, starting at 4:30pm CDT / 19:30 UTC, the site will be undergoing scheduled maintenance for a few hours. During this time, the site might be unavailable for a short while. Thanks for your patience.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How to force a story status to change from ToDo -> InProgress when user logs time

Scott Hassell June 7, 2022

Some users are not moving a story status from ToDo -> InProgress when they log time.  Is there a way to force a status change based on when time is logged?

1 answer

1 vote
Sreenivasaraju P
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 7, 2022

Hi @Scott Hassell ,

You can achieve this using Automation. 

There is an Issue trigger called , work logged.  When this is triggered, you can select the new action as component and select transition issue.

This may help you.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events