×Hello,
I am trying to figure out a way to set a due date on a subtasks based on a task due date via automation. I am using smart values to add few business days. I can't figure out how to make the business day reflects our calendar which is Friday and Saturday are the weekend. I have tried to modify the board setting but I am pretty sure this is not where to look.
I have looked at the system time tracking but it doesn't offer option to modify this setting.
Unless this only only works with Service Management and Calendar's SLA settings
Thanks
You are correct, Jira Software allows working days configuration only for Sprint Boards , unlike Jira Service Management projects where you can configure the Calendar SLA.
Cheers
Ajay