How to update Due date based on Create date using Jira automation

Rajesh Konda
Contributor
January 11, 2023

Hi All,

 

I have a requirement to update due date to +2 days based on create date during a transition. Tried using Jira automation but unable to update based on created date. Able to update with Now function, it gives us based on current time and date but i need based on create date. Please suggest in doing this task. Thanks

Tried Smart Values : {{issue.create.PlusBusinessDays(2)}}, {{issue.create.Days(2)}}  

1 answer

1 accepted

1 vote
Answer accepted
Ste Wright
Community Champion
January 11, 2023

Hi @Rajesh Konda 

This should work as a smart value:

{{created.plusBusinessDays(2)}}

Ste

Rajesh Konda
Contributor
January 11, 2023

Thanks a lot @Ste Wright , above smart value worked for me. Thanks again.

Like • 3 people like this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
atlassian, jira product discovery, jpd premium, product management, idea management, product discovery, jira premium, product planning, atlassian community, product development, roadmap planning, product prioritization, feature management

Introducing Jira Product Discovery Premium ✨

Jira Product Discovery Premium is now available! Get more visibility, control, and support to build products at scale.

Learn more
AUG Leaders

Atlassian Community Events