I want to see that if a team is starting with 10 tickets for a goal, but at the end of the sprint they pivoted and added 5 new tickets it would show a % change from the originally committed items.
The Velocity Report will show you the total Committed and Completed for a sprint based on your Estimation Statistic, but it will not show that as percentages.
Committed overall Completed makes sense. So say we finished 30 points, but 10 of those were because we took out 10 points and added a different 10 points midsprint. Thats the number I want.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Burndown and Burnup Chartst will show you scope changes in your sprints. The list at the bottom of the page shows the scope change on a per issue basis, noting if issues were added, removed, or had their points changed.
There is not a single report that will otherwise provide both summary and detail for the Commitment, the Completed, and the details of changes between those numbers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.