When I have spillovers from one sprint to another, I close the current sprint and choosing the next sprint in the popup dialog for not done issues. What rank are those issues getting when its adding to the next sprint (not opened yet, relatively to the issue were in there already).
Hope the question is clear.
Nofar
Issues in current sprint are ranked higher than issues in the backlog. If you have more than one sprint created, then the next sprint is first, with the others descending in rank as they get further away.
Ans issues moved from the sprint I closed to a new sprint? what is their rank relative to issues were in the new sprint already?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
From memory, above, because they should have been completed in the last sprint, and made it into the last sprint because they were higher ranked than the current sprint items.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.