when a subtask do a transition
Moving from backlog /open to inprogress
If
it is an open sprint
If the parent task is in (backlog/open)
Than move the parent task to (Inprogress)
Else
If the parent task is in (open)
then move the parent task to ( Inprogress)
Hi Team,
PFA automation rule.it audit log it is now showing the status expect "Configuration change"
Please help
Thanks,
Anil
Hi @Arnav,
Your conditions are in the wrong place in the rule. The should come before the For Parent branch. So:
(your initial trigger already implies that the sub-task you start from is in progress, so no additional validation of statuses would be needed)
Hope this helps!
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.