Populate Sprint field for Bugs and sub tasks

Krishna Chaitanya Vitalapuram July 11, 2023

i created a rule to Populate Sprint field for Bugs when linked to a story. However it is not working. I am unable to find whats wrong. Please suggest

2 answers

0 votes
Trudy Claspill
Community Champion
July 11, 2023

While I agree with @Nic Brough -Adaptavist- that adding new Bugs to your Sprint automatically is not a best practice, I'm willing to advise you on how to change your Automation Rule.

Please show us the full Automation Rule you have. Show us the Audit Log for an execution of the rule where it did not do what you expected.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 11, 2023

Welcome to the Atlassian Community!

Sub-tasks are not sprint items, they do not go into sprints individually, they are included in a sprint when the issue of which they are a part is in a sprint.  (I'm guessing your bugs are probably a sub-task type too).  The sprint field is an irrelevance in a sub-task because it's part of something else.

Krishna Chaitanya Vitalapuram July 11, 2023

Hi Nic,

 

Thanks for the response. No , i am crreating issue type = bug and then linking to a story. When i link it and if the sprint value of the bug is empty then the sprint value of the bug to be added similar to the story

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 11, 2023

So your "bugs" are at the same level as stories?  

You should not be just adding bugs into a sprint when they are created and linked - your developers should be adding them into their sprint during sprint planning.

Krishna Chaitanya Vitalapuram July 11, 2023

Agree with you but at org level this is being expected. So have to create automation rule for the same

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 11, 2023

What your org level expects is not Scrum, it's not Agile, and it cannot work, for sub-tasks.  If your bugs are at the story level, you can do it for them, but sub-tasks simply can't have a sprint field applied to them, other than inheriting it from their parent.  It's total nonsense to have a sub-task that's in a different place to the thing of which it is a part.

Krishna Chaitanya Vitalapuram July 11, 2023

right now iam looking only to add sprint value to bugs not to sub-tasks