I want to specify in my query to make sure I'm only retrieving tickets that were changed from one status to another within 7 days. So, in my example, if the status of the ticket was "Closed" then 6 days later it changed to "Customer Response", I want that ticket to be included:
Assignee in (LIST OF ASSIGNEES)
and createdDate >= '2022-03-01' and createdDate <= '2022-03-31'
and
(
status changed from "Completed" to "Closed"
and status changed from "Closed" to "Customer Response"
and status changed to "Customer Response" XXXXX
)
or
(
status changed from "Cancelled" to "Closed"
and status changed from "Closed" to "Customer Response"
and status changed to "Customer Response" XXXXX
)
Where I have written XXXXX I assume I need some sort of logic, but I'm not sure how it would be written. Any help would be appreciated.
Hi @Alex ,
You can do that by utilizing DURING like so:
Assignee in (LIST OF ASSIGNEES)
and createdDate >= '2022-03-01' and createdDate <= '2022-03-31'
and
(
status changed from "Completed" to "Closed"
and status changed from "Closed" to "Customer Response"
and status changed to "Customer Response" DURING (startOfDay(-6), startOfDay())
)
or
(
status changed from "Cancelled" to "Closed"
and status changed from "Closed" to "Customer Response"
and status changed to "Customer Response" DURING (startOfDay(-6), startOfDay())
)
Utilizing DURING requires you use a start and end date. In the above example, I used startOfDay(-6) as the start date, meaning the start date will be the beginning of 6 days ago. I used startOfDay() as the end date, meaning the end date will be the beginning of today.
Hi Josh - this looks good but instead of referring to today's date I need to be looking at the date of the status's. So for example, I need it to show tickets that were moved in to the Customer Response status from the Closed status with 7 days of them being in the Closed status.
So if we're looking at a ticket which was Closed on the 1st of March which moved in to Customer Response on the 3rd of March, I need it to be pulling those tickets back. I think your solution is looking at todays date instead of referring to the dates of the status's.
Sorry this is a bit tricky to explain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Alex
I have done a bit of research and I don't think we can accomplish what you're looking for. It does not appear that there are dates associated with the statuses; only dates for the issue itself.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.