We have three boards on a company-managed project and we need each board to capture the requirements for each product that we're working on for the same client. All the requirements are in the backlog of the project but we don't know how to add the requirements (user stories and tasks) to each board, each board should have different requirements because the products are different. Is there a way we can add a set of requirements (user stories and tasks) to a board and then add another set of requirements (different from the first set) to our second board?
Hello Emily,
what type of boards do you use?
When you are using Scrumboards than you must start a sprint otherwise you will not see any tickets on the board.
Apart from this each board represents a filter behind it.
You can easily build a new filter eg. project in (ab, abc) and type in (task, bug).... so that only certain projects and issue types are displayed on the board.. and another for the other board..
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.