Hi,
We are currently trying JIRA agile. We saw in many post that people can set an original estimate for subtasks but for us, it's just seem that this functionality doesn't exist.
Is somebody can put us on the right way to do it?
Hi Kenjy,
What's probably happening is that the Time Tracking fields are not present in the screens associated to your sub-tasks. Could you please check on that?
Cheers,
Clarissa.
Thank you, my problem is now resolved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Clarissa, the "Time Tracking" fields are for tracking, but Kenjy had asked about Original estimate. I thought tracking and estimate were separate in Jira?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.