Hi All. Need support to figure out the issue.
Project Structure :
Epic
--> Task
-----> Sub-Task
1. Earlier i use to indent or Outdent Tasks/Sub-Tasks in BiGpicture and it automatically creates Issues Links("Split From" or "Split To") in the respective tasks, but currently this automatic Links creation is not working and requires manual update in the Issue link field.
Q - Any workaround available?
2. Outdenting Task is only possible within Root Epic, but outdenting task to link with other root Epic is also not working.
Q - Any workaround available?
Hi Raj,
Thank you for your feedback.
1. I'm not sure if you are talking about the task structure builder. You can assign auto structure box configuration -> task -> task structure ->
or if it is related to the creation of links in Jira as in our feature request available here: ONE-7212 - please open it in incognito mode.
2. When your task builder is enabled ( sorted on epics ), you are not able to modify tasks below epics. Please clear your builder; it should help you to change it in the structure.
I hope it helps.
Best regards,
Rafal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.