Hi,
By default presented with Issue Types - EPIC - BUG - STORY - TASK.
If adding a new issue type for example INITIATIVE, how do I make this the top level issue type.
ie. INITIATIVES are made up of EPICS... EPICS are made up of STORYs... STORYs made up of TASKs.
Hi Simon!
If I understand you correctly, you want to set a custom issue type called "Initiative" as the highest level of issue in your instance.
To do this, you have to go here and add it:
Hit the "Create level", add the "initiative" issue type and arrange them at your own will.
Remember to click "Save Changes".
Also: Changes to the hierarchy configuration will only apply to plans in Advanced Roadmaps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm trying to do the same thing, and create a 5 level hierarchy with a few new types, and t's letting me create the types, but it doesn't seem to be allowing me to establish the hierarchy I want? Thoughts? I want Project --> Stage --> Epic --> Story --> Task --> Sub Task, with Milestone and Deliverable as additional Sub Tasks...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.