Hello,
We are seeing issues with estimates being rolled up to the parent issue. I do not see the estimates neither in original / time remaining estimates field nor in their auto sum fields.
Scenario:
I have checked Time Tracking field is added to the screens. Board configuration has radio button Original and Time Remaining selected.
Please advise.
Thanks
Sunil M.
Why hasn't this been answered yet? This seems like a no brainer yet it's not implemented?
See also: https://jira.atlassian.com/browse/JSWSERVER-15626
It looks like people are using Structure and other plug-ins to get reasonable roll-up behavior out of JIRA.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.