Advance roadmap auto schedule with holidays?

Nicolas SARRABAYROUSE November 10, 2023

Hello,

I hope an auto scheduling taking into account holidays of people >> is-it possible with Advanced roadmap? I searched a part of day without success!

 

Thank you :-)

2 answers

1 accepted

1 vote
Answer accepted
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 10, 2023

Hi @Nicolas SARRABAYROUSE Welcome to the Atlassian Community!

That is not possible, see: How does the Auto-scheduler in Advanced Roadmaps work?

Matt Doar
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 10, 2023

If your plan uses Agile boards, you can add holidays to the agile boards to do this. But not directly in plans

Like Dave Mathijs likes this
Nicolas SARRABAYROUSE November 13, 2023

Hi Dave,

Thank you for you answer,  I don't understand the interest of an automatic scheduler which don't take into account availability of people.

Is there an optional "App" doing that (for Sprint but also in a Waterfall project)

0 votes
Yuliia Hushcha _Reliex_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 24, 2023

Hi @Nicolas SARRABAYROUSE 

ActivityTimeline plugin is a great option for holiday management. You could schedule tasks taking into account the holidays of people but its will be assigned without considering the priorities of tasks. The add-on also has an integration it with Advanced Roadmaps & Jira teams. 

If you have any additional questions, please feel free to ask me. We can provide a demo session for you if need it.

Nicolas SARRABAYROUSE November 28, 2023

Thank you for your answer Yuliia,

Well I need to keep auto-scheduling on priorities (for me it is the main feature with resource leveling).

Best regards,

Nicolas.