We want to pull velocity from Sprint 0 to Sprint 5 (FYI we are running sprint 10). But Velocity Report can show only 7 recent sprints. So how to retrieve velocity info of old sprints.
Thanks in advance.
-Bala
You can also use the Sprint Report to view any past Sprint. It will give you a total of completed story points (or whatever you are using for your estimates) which is the velocity for the Sprint - it appears at the top of the first table (Completed Issues) below the graph.
https://confluence.atlassian.com/display/GH/Viewing+the+Sprint+Report
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
A velocity report is useful in helping to predict how much work can be completed by the team in a future sprint, based on recent work. Currently the Velocity Chart is hardcoded to show (max) last 7 sprints, but there's an improvement request (GHS-6034) to have the ability to show all sprints within a project.
Feel free to vote for it to increase its visibility, and add yourself as a watcher to keep track of its progress.
Hope it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Quick help needed pls.
I have a team dashboard where I capture the velocity of the team for various sprints. Currently, we are in the third sprint and for some reason, the velocity chart pulls up old two sprints i.e Sprint-1 & Sprint-2. But it also pulls up some other sprint the chart. This happens when I (Uncheck ) Sprint name contains.
When I check Sprint name contains it only pulls up only one sprint that's mentioned in the field. Did anyone encounter such issue?
I have other boards with the same options they all seem to pull the right sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramya, how did you create a dashboard showing the velocity? Did you use their gadgets?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have same question. How do we create dashboard showing velocity of older sprints.
For me in "Velocity Chart" reports it just shows last completed sprint. And in Sprint report, I can check "completed", "not completed", "removed", "completed outside sprint", and i need to do some maths if there are tickets which were added/removed after sprint started.