Hello,
I am new to JIRA. Currently i have a milestone and want to mark completed. All the stories and defects in it are marked as DONE (custom flow). when i trigger completee sprint it always show open issues. How can i make it work?
Make sure the last column of your board has the done status issues. Also be sure to set the Resolution field when moving to Done.
@Jack Brickey : Thanks for sharing your thoughts. As you said, after moving issues to last column in the board, it started reflecting. Thanks a lot.