Hi
I have a pretty cool looking chart when I am showing epics/issues within on projects.
However, I am hitting a snag when I try to include issues from other projects using the 'filter' approach.
I structured a Jira project with epics and a 'roll-up' issue type I created. So far so good.
The 'roll-up' issues represent activities that will be performed by other teams. Those teams have their own Jira projects. I have tagged those issues so they can be included in the filter I am using for the Gantt.
The snag I am hitting is that the tasks in other projects are showing up in a separate section. I would like/expect them to by displayed under the the roll-up issue.
Is there a way I can associate the roll-up and the activities, and have them displayed in a hierarchy?
Thanks
Hello @Phil McTimoney ,
I totally understand what you would like to do, but unfortunately, it is not possible to have a hierarchy across Jira projects. The feature request is already posted on our Productboard.
We're sorry for the inconvenience.
Best,
Hal
Ricksoft
Thanks for the prompt response. I have added my comments to the feature request.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you so much for providing us with valuable feedback! We'll do our best to make the app better.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.