×I wanted to reopen a closed sprint. The support section says in reports you will find the "sprint report". There you can see all sprints and reopen a closed sprint. But there is no sprint report. It seems that this applies for classic only. Any suggestions for next-gen?
Unfortunately you cannot re-open a sprint in Next Gen at this stage - you can vote for the inclusion of this feature though here: https://jira.atlassian.com/browse/JSWCLOUD-17208