Sprint is both Future and Current

Alex Romano
Contributor
December 17, 2020

We often assign sprints by manually selecting them from the drop-down in the right pane of a card.

 

Recently, the contents of the drop-down changed in an unexpected manner.

Previously, as we clicked in the field, it would show something like:

Dev Sprint 120
current

Dev Sprint 121
future

and so on.

Now, we find:
Dev Sprint 120
current
Dev Sprint 120
future
Dev Sprint 121
future

We could ignore it, but not all views offer the current vs future distinction label.
Help?

1 answer

1 accepted

0 votes
Answer accepted
Alex Romano
Contributor
December 17, 2020

Pretty sure I can answer my own question.
Two projects display on the board we use for a combined sprint, but they are each scrum in and of themselves and some sprints were accidentally created in one of the individual projects as well as in the shared scrum board. Removing the sprints created in the backlog of the individual project solved the issue.

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 22, 2020

Hi @Alex Romano 

Would you please mark your own question as answered?  That will help others in the community find solutions faster if they see the same symptom.  Thanks!

__Bill

Alex Romano
Contributor
December 22, 2020

@Bill Sheboy Thank you for the gentle reminder, will do.

Like Bill Sheboy likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events