Sum up to Epic the original estimate

Sofia Quintero
Contributor
December 7, 2021

Hello i´m working on a automation to sum up the original estimate of tasks that are in epic.
I´ve already check this article. And the solutions works for task-subtask level, not for epic. Olso i´ve tried using the smar values with the log of the field.

Did anybody achived a requierement like this without add-on?

The smart values tried:

{{#=}}({{fieldChange.to}} - {{fieldChange.from}} + {{issue.original estimate}})/60{{/}}

{{#=}}({{fieldChange.to}}/60 - {{fieldChange.from}}/60 + {{issue.original estimate}}/60){{/}

{{#=}}{{issues.Original estimate.sum}} /60 {{/}}

 

1 answer

1 accepted

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 7, 2021

Hi @Sofia Quintero 

Yes, and to what Trudy suggests:

The Lookup Issues action now supports most fields, and so you may be able to sum up the values with a JQL statement and Lookup Issues for the types you want without a work-around to use the Story Points to hold the values..

Kind regards,
Bill

Like # people like this
Sofia Quintero
Contributor
December 7, 2021

Thank you @Bill Sheboy , you´re always ready for answer. i´ll check it out.

Like Bill Sheboy likes this
Sofia Quintero
Contributor
December 9, 2021

Thank you @Trudy Claspill  for the article! It worked!

Suggest an answer