We did a workflow change, but mistakenly mapped all the closed and resolved issues into done by dev state which is open now! I now have more than 3500 issues trying to load in my Backlog.
Also, some developers can’t see the board as well.
Got any clue how to move back those thousands of issues to the closed state?
You can try running the JQL query to retrieve all the issues whose status was changed from XYZ to ABC and do the bulk update.
project= "project key" and status changed from XYZ to ABC
Hope this helps.
Thanks,
Vamsi
Hi Vamsi,
Thank you for responding, it indeed helped and I was able to solve my issue.
Regards,
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.