Hi Lilit
When you complete a sprint and select to move the incompleted issues from current Sprint to the next Sprint or backlog, Jira save the current sprint value in the Sprint field. Therefore, you can filter the not completed issues by jql like
project = project name and sprint in "sprint id" and status != closed
In your backlog view, click the icon "View in issue navigator" beside your Sprint, you will find the sprint id.
the Sprint id is the id for the completed sprint