Hi all,
As part of an internal review, under Time Tracking we are looking to change the "Day" value from 8 hours to 7.6 hours.
Before we proceed with this change, what impact will this have on all previously logged time?
There is a concern that if we make the change, it will interfer with all existing tickets, leading to confusion around reporting.
Any help would be greatly appreciated,
Cheers,
Barry
Should have no impact, since as far as I know Jira uses minutes for the calculation in connection to the current used settings in the time tracking configuration. But your former entries will be adapted, because a 5 day week has no longer 40 hours but 38 hours. So an existing time estimation of 1w will then be 1w and 2h.
Hi Barry & Jose,
Just want to confirm the above behaviour in OnDemand is correct. An issue previously estimated as 1w will adjust to 1w2h upon changing the 'The number of working hours per day' to 7.6.
Cheers,
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.